RCC formwork must be properly prepared before pouring concrete in it. Following checklist ensures all checks are complete to ensure good quality RCC work.
| Sr | Check Item | Done |
| 1 | Check the formwork is properly aligned. | |
| 2 | Check it is cleaned. | |
| 3 | If framework is steel, check it is oiled. | |
| 4 | If framework is wooden, check inner surface is smooth. | |
| 5 | Check if the formwork is water-tight. | |
| 6 | Check supports are properly placed and fixed. | |
| 7 | Check width and depth/height of formwork. | |
| 8 | Check thin metal sheets are provided along joints of wooden framework. | |
| 9 | Check foam is provided along the joint of steel formwork. |

