Tunnel Engineering Quiz 01

Advertisement

Circular section of tunnels is not suitable for :

Correct! Wrong!

What is the correct sequence of the following events of construction of a shaft in rock ? 1. drilling and blasting 2. timbering 3. pumping 4. mucking Select the correct answer using the codes given below Codes :

Correct! Wrong!